News

Months after a massive battery plant fire, the PG&E facility next door was ready to get back on the grid. But the company ...
PG&E announced they would be shutting back down their battery storage facility because of technical issues.Never Again Moss ...
Pacific Gas & Electric is delaying reopening its Elkhorn battery storage facility after identifying equipment malfunctions.
The new interactive dashboard allows users to find results of water and soil testing, in addition to screening results ...
The survey, completed by 1,539 individuals, indicates that 83% experienced at least one symptom, most commonly headaches, ...
The Monterey County Herald on MSN4d
Moss Landing clean water project breaks ground
A score of residents will be consolidated into a safe water system operated by the Springfield Water System in the area of ...
So far, this process only includes batteries that were not damaged by the fire. Crews are working to uncharge them and plan ...
A wave of lawsuits, large and small, have been waged against Vistra Corporation, PG&E, and many of their associated companies in the months following an explosive Jan. 16 fire at their battery storage ...
PRUNEDALE>> A community group of about 30 gathered last week at Prunedale Grange to share their frustrations about what they feel is a lack of information in the aftermath of the Moss Landing ...
MOSS LANDING — Flames continued to spew early Friday morning in the community of Moss Landing and the Elkhorn Slough area in northern Monterey County after a major fire at a battery storage ...
PG&E said that after discovering a few issues, they are delaying the start of their Elkhorn battery storage facility until ...
The grassroots group of residents, calling themselves “Never Again Moss Landing,” are fueled by concerns over environmental and health impacts of the fire that broke out Jan. 16 at the Vistra ...